C
Carolina
I have this doubt, Is the Olap Cube update doesn't consider the projects when
they're open? I will tell you the whole history:
A PM does not see the resources assignment changes for the team on the
Portfolio Analyzer. She assured me she made the changes before the Olap Cube
was updated. Off course I didn't believe her and after looking into the
change using Project Proffesional, I asked her to published and I update the
OLAP Cube again.
When I check the Portfolio Analyzer, the update was not performed for her
project. Then I realize that she still have her project open. She closed it
and I update the Olap Cube again, now it works. Is there any restriction to
update the cube that does not consider the projects open?
Thanks in advance
they're open? I will tell you the whole history:
A PM does not see the resources assignment changes for the team on the
Portfolio Analyzer. She assured me she made the changes before the Olap Cube
was updated. Off course I didn't believe her and after looking into the
change using Project Proffesional, I asked her to published and I update the
OLAP Cube again.
When I check the Portfolio Analyzer, the update was not performed for her
project. Then I realize that she still have her project open. She closed it
and I update the Olap Cube again, now it works. Is there any restriction to
update the cube that does not consider the projects open?
Thanks in advance