M
mattn
Dear all, please be gentle - a newbie to Project.
I run the installations of a local kitchen/bathroom firm. We have up to 15
fitters/plumbers/tilers etc working on around 30-40 live projects with a
turnaround time per project from 2 hours to 3 or 4 weeks.
The main problem we have is the rapidity of change to schedules.
Is Project the answer to my dreams of a system of allowing the whole company
visibiltiy to the installations status? or will IU have to go the whole hog
and head down the MRP route...
Any thoughts/suggestions would be gratefully received
much thanks
mattn
I run the installations of a local kitchen/bathroom firm. We have up to 15
fitters/plumbers/tilers etc working on around 30-40 live projects with a
turnaround time per project from 2 hours to 3 or 4 weeks.
The main problem we have is the rapidity of change to schedules.
Is Project the answer to my dreams of a system of allowing the whole company
visibiltiy to the installations status? or will IU have to go the whole hog
and head down the MRP route...
Any thoughts/suggestions would be gratefully received
much thanks
mattn