A
anovak
We have a major ERP upgrade going in fairly soon with about 7
sub-plans, each representing a specific module activity.
There are two sibling organizations that will be impacted by the
upgrade - two seperate and distinct sets of user communities that share
the same database.
The plan in the beginning was to have a project lead for each of the 7
sub-plans, a person selected at one of the sibling organizations who
would be coordinating with the other organization and reporting up to
the project manager.
Now, it is desired that there be co-project leads for each sub-plan,
one at each sibling institution.
Therefore, the result will be 14 plans instead of 7, with an individual
project lead in each organization responsible for keeping their project
plan updated. That is, for the Module A plan, there will be an
identical plan for Organization A and Organization B. I'm gathering
the main difference will be some of the resources assigned and
especially the Project Lead responsible for keeping the plan (manually)
updated. There may be some task differences, but I'm not aware of
those as of yet.
The milestones will be identical in both and each are required to reach
the milestones at the same time.
Timesheets will NOT be used. As mentioned earlier, the plans will be
updated manually.
Is there a better approach to this than duplicating the project plan
for each organization?
Thanks,
Andy Novak
University of North Texas
sub-plans, each representing a specific module activity.
There are two sibling organizations that will be impacted by the
upgrade - two seperate and distinct sets of user communities that share
the same database.
The plan in the beginning was to have a project lead for each of the 7
sub-plans, a person selected at one of the sibling organizations who
would be coordinating with the other organization and reporting up to
the project manager.
Now, it is desired that there be co-project leads for each sub-plan,
one at each sibling institution.
Therefore, the result will be 14 plans instead of 7, with an individual
project lead in each organization responsible for keeping their project
plan updated. That is, for the Module A plan, there will be an
identical plan for Organization A and Organization B. I'm gathering
the main difference will be some of the resources assigned and
especially the Project Lead responsible for keeping the plan (manually)
updated. There may be some task differences, but I'm not aware of
those as of yet.
The milestones will be identical in both and each are required to reach
the milestones at the same time.
Timesheets will NOT be used. As mentioned earlier, the plans will be
updated manually.
Is there a better approach to this than duplicating the project plan
for each organization?
Thanks,
Andy Novak
University of North Texas