Steve House [MVP]

You have a couple of choices. You can set up an Enterprise Global calendar
in Project Server if you are using that and want your celndar to be avaiable
to all the PMs developing projects, or, if you're not yet using server,
create a calendar (I'd suggest using a copy of the Standard calendar so you
retain the master, although you could edit the Standard if you wish) in the
current project file, could even be a blank project, that shows all the
holidays etc for a convenient time period. Then, use the Organizer on the
Tools menu to copy the customized calendar in the working project file back
into the Global.MPT template to make it available to all other projects.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
 