I'm a noobie using Project 2003. I know how to set a task duration
and also use elapsed time duration. However, what I want to do is the
following: I have a task that requires e.g. 8 hours (or 1 day), but
it needs a full working day, it shouldn't be split. It's linked to
the previous task in order to start. So that task finishes with 2
hours left in the day and then starts my task of interest. It does
that task for 2 hours on that day and then six hours on the next day.
Is there a way I can set the property of the task to require that it
can only start if it has a full day and cannot be split? The only
thing I know of is to set the start date of that task or require a
start no earlier date, etc. But then if I change the timeline
upstream it will not automatically change with it, I'll have to change
that starting date again.
Thanks for any and all advice in advance!
Jack Rowan
and also use elapsed time duration. However, what I want to do is the
following: I have a task that requires e.g. 8 hours (or 1 day), but
it needs a full working day, it shouldn't be split. It's linked to
the previous task in order to start. So that task finishes with 2
hours left in the day and then starts my task of interest. It does
that task for 2 hours on that day and then six hours on the next day.
Is there a way I can set the property of the task to require that it
can only start if it has a full day and cannot be split? The only
thing I know of is to set the start date of that task or require a
start no earlier date, etc. But then if I change the timeline
upstream it will not automatically change with it, I'll have to change
that starting date again.
Thanks for any and all advice in advance!