E
Eric
I have created a master project schedule with approximately 60 sub-projects.
I then resourced my staff of 6. My goal beyond project planning is analyzing
our staffing levels. I am very close and I am currently tweaking working and
non-working times.
I am wondering if there is a generic way to represent non-working
(unavailable) time without assigning specific dates. The only method I have
come up with so far is calculate a percentage based on total working hours
and subtract that time from their available time. I would like to see if
anyone has come up with something more creative.
I then resourced my staff of 6. My goal beyond project planning is analyzing
our staffing levels. I am very close and I am currently tweaking working and
non-working times.
I am wondering if there is a generic way to represent non-working
(unavailable) time without assigning specific dates. The only method I have
come up with so far is calculate a percentage based on total working hours
and subtract that time from their available time. I would like to see if
anyone has come up with something more creative.