Is there a way to see on what date a resource entered time?

J

JenStover

We are on 07 through April CU.

I want to know on what dates my folks are doing the actual entering of their
hours. Is there a way to find this out?

i.e. on 11/20, Bill entered 4 hours worked on 11/16.

Thanks!
 
D

Dale Howard [MVP]

JenGoSto --

To expand on my cousin Ben's reply to your question, you can see when a
resource submitted a task update, but you cannot see when they actually
entered the data. To see when they submitted a task update, click the name
of the task in the Task Updates page. The system opens a dialog that shows
you quite a bit of information about the task update. Hope this helps.
 