K
KDB
The "Format, Layout" command appears to be either "on" or "off" for all tasks
with predecessor/successor relationships. For reasons I won't go into, a
request came up at my work where someone only wanted to show the link lines
on the Gantt view for key/important/specified tasks (not show all of the
linking lines between "unimportant tasks"). Is there a way to do this?
Obviously you could "fake" the system out by using hard/constraint start/stop
dates (instead of using predecessor/successor relationships) on all of the
tasks where you don't want link lines to show; or, turn-off the link lines
feature in the Layout command and 'draw' lines/arrows using the drawing
toolbar features of Project. Both of these approaches would be, of course,
cumbersome.
with predecessor/successor relationships. For reasons I won't go into, a
request came up at my work where someone only wanted to show the link lines
on the Gantt view for key/important/specified tasks (not show all of the
linking lines between "unimportant tasks"). Is there a way to do this?
Obviously you could "fake" the system out by using hard/constraint start/stop
dates (instead of using predecessor/successor relationships) on all of the
tasks where you don't want link lines to show; or, turn-off the link lines
feature in the Layout command and 'draw' lines/arrows using the drawing
toolbar features of Project. Both of these approaches would be, of course,
cumbersome.