Hi,
I have defined the Fiscal Periods in PWA.
I want to use the same periods in the task usage view in Project
professional, so that we can the 4,4 and 5 distribution of weeks for the
quarters per month in it.
This way we can see the hours for each month looking like July -160 , august
-160 September 200 and so on.
Can this be done in Project professional?
Thanking in advance!