R
Rick Anderson
This question is not specific to Project 2003 (same behavior in 2000 and
2007). Let's say I have a project that starts on Monday, 1/28/2008 and
consists of four 5 day tasks (task #1, task #2, task #3 and task #4). Each
task is assigned to the same person, and they are each successors of the
other. So one would expect the critical path to be task #1 for 5d, task #2
for 5d, task #3 for 5d and task #4 for 5d. If we review the critical path,
that's what it shows us.
Now, instead of working on task #1 on 1/28/08, I complete 1 day of work on
task #2. At this point, my critical path becomes task #2 -> #3 -> #4 and #1
drops off the critical path. I can't convince myself this is correct. I
still have 5d to do on that task and it's clearly part of the critical path
chain. Project says task #1 has 1d of slack, which is why it is not showing
up.
What is the best way to get around this? We often have tasks that start out
of order. I suppose we could break them up into smaller parts (the part that
started and the part that is left), or we could re-organize predecessors and
successors, but it seems like there must be some better way.
If I change task #1 to start on 1/22, it shows back up in the critical path.
That seems simple enough, but a more complex example of where task #1 has 1d
complete and task #2 has 1d complete makes this less desireable (so start
task #1 on 1/22, mark task #1 as 1d complete and mark task #2 as 2d complete
and #1 is back off the critical path and interestingly task #1 has no slack
in it).
If you play with this simple example, there is all kinds of interesting
things that happen if you change start dates and so on.
I appreciate any help. It's driving me a bit nuts.
Rick Anderson (rick dot d dot anderson at tektronix dot com)
2007). Let's say I have a project that starts on Monday, 1/28/2008 and
consists of four 5 day tasks (task #1, task #2, task #3 and task #4). Each
task is assigned to the same person, and they are each successors of the
other. So one would expect the critical path to be task #1 for 5d, task #2
for 5d, task #3 for 5d and task #4 for 5d. If we review the critical path,
that's what it shows us.
Now, instead of working on task #1 on 1/28/08, I complete 1 day of work on
task #2. At this point, my critical path becomes task #2 -> #3 -> #4 and #1
drops off the critical path. I can't convince myself this is correct. I
still have 5d to do on that task and it's clearly part of the critical path
chain. Project says task #1 has 1d of slack, which is why it is not showing
up.
What is the best way to get around this? We often have tasks that start out
of order. I suppose we could break them up into smaller parts (the part that
started and the part that is left), or we could re-organize predecessors and
successors, but it seems like there must be some better way.
If I change task #1 to start on 1/22, it shows back up in the critical path.
That seems simple enough, but a more complex example of where task #1 has 1d
complete and task #2 has 1d complete makes this less desireable (so start
task #1 on 1/22, mark task #1 as 1d complete and mark task #2 as 2d complete
and #1 is back off the critical path and interestingly task #1 has no slack
in it).
If you play with this simple example, there is all kinds of interesting
things that happen if you change start dates and so on.
I appreciate any help. It's driving me a bit nuts.
Rick Anderson (rick dot d dot anderson at tektronix dot com)