I have a very simple macro which works out the planned % complete relative to
the status date and puts it in a field for me. I then use the MSP actual %
column and compare the two. Works fine until the Summary Bar. I have posted a
question in the General section and I now fully understand how MSP works out
the % complete. Is there a VBA/Macro Genius out there who can help me
replicate how MSp works out the actual % and use it to give me the planned %
against a Summary Bar. My macro works out the % complete in a straight line
whilst MSp uses accumulated work content. This would have to be able to
differentiate between each section of work ie summary sub-set
Many thanks in advance
the status date and puts it in a field for me. I then use the MSP actual %
column and compare the two. Works fine until the Summary Bar. I have posted a
question in the General section and I now fully understand how MSP works out
the % complete. Is there a VBA/Macro Genius out there who can help me
replicate how MSp works out the actual % and use it to give me the planned %
against a Summary Bar. My macro works out the % complete in a straight line
whilst MSp uses accumulated work content. This would have to be able to
differentiate between each section of work ie summary sub-set
Many thanks in advance