Issue Adjust actuals - Conflicts with Project Server Database

C

candid

Hi,

I hope someone can help us with the following problem.

In one of the projects we have, we need to adjust some actuals that
are entered. It's a pretty simple project with only 2 tasks. However
when adjusting the actuals via PWA we get the message:

"There is a problem Updating the task information because of conflicts
with the project server database. Contact the Server Administrator
about these tasks. Some actuals were not updated."

We do not have this issue with other projects.

I've already save the project as a file and re-imported it, but that
didn't seem to help.

All tips, remarks,... are much appreciated!

Kenneth
 
M

Mike Glen

Hi candid,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 
M

Mike Glen

Hi candid,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top