T
Tuckey
Hi! My company is in the process of rolling out onto PS 07 (we are upgrading
from PS 03). We've put on service pack 2, followed all the directions, got
our server up and running with the new time phase view in My Tasks. When we
had done initial testing with dummy projects the time phase worked GREAT!
Prefect for us since we only want to track project time and not make it too
confusing for our users with having to import between timesheets and tasks
(resources do need to be babied and cuddled to keep them happy!). We have
our Task Settings and Display set up as follows:
Tracking Method: Actual work done and work remaining
Force project managers to use the progress reporting methods specified above
for all projects (Yes this is checked so that PMs can’t use anything else)
Reporting Display: Resources should report their hours worked every day
Week starts on Monday
Protect user Updates: Restrict updates to Project Web Access
Define Current Tasks: Ours is set to 14 Days
Enabled Team Member Gantt view: This is enabled
Currently we have our My Tasks view grid to display this information (this
was at the requests of the PMs but if you have an arrangement that would be
better I will gladly suggest it to them. Yes, I did make them aware that
with Actual Work Done the tracking progress does not automatically capture an
actual start or finish date but this is what they wanted):
Task Name, Start, Actual Start, Remaining Work, week dates, Finish
We have not changed anything on the settings since moving from dummy
projects to real projects but now we cannot enter time into My Tasks. When
we drill down into a task we also no longer see the time phase grid there
either. I’ve tried opening up all the projects and resaving them and then
republishing them to make sure they are definitely all using the same
tracking method but this has not helped either. We can however, change the
Start, Actual Start, Remaining Work and Finish columns. The days a tasks is
scheduled does highlight like it will allow you to input information but the
days the tasks is not schedule for it doesn’t highlight at all.
I don’t know if this means anything but we have our timesheets turned off
and not displayed in the Quick Launch since it was decided to only enter time
into My Tasks.
In regards to Assignment Owners, if we assign our functional/resource
managers as his/her resource’s owner will both the resource and the manager
see the task in their My Tasks page? Our functional/resource managers want
to see all the tasks his/her resources are assigned. We would like to make
it that if the resource that the PM assigned to a project had and emergency
the manager would be able to reassign the task to a different resource (after
that informed the PM of course) so the project plan doesn’t get pushed out
due to the unavailable resource. If using Assignment Owners do not allow
both the manager and resource see the tasks do you have any suggestions on
how we can make it so managers can see the tasks his/her team is working on
in Project Web.
If my questions aren’t clear I am sorry! I tried to provide as much
information as I could. If you are not sure what I am asking please let me
know and I will try to explain our situation better.
Thank you in advance for all your assistance!
Tuckey
from PS 03). We've put on service pack 2, followed all the directions, got
our server up and running with the new time phase view in My Tasks. When we
had done initial testing with dummy projects the time phase worked GREAT!
Prefect for us since we only want to track project time and not make it too
confusing for our users with having to import between timesheets and tasks
(resources do need to be babied and cuddled to keep them happy!). We have
our Task Settings and Display set up as follows:
Tracking Method: Actual work done and work remaining
Force project managers to use the progress reporting methods specified above
for all projects (Yes this is checked so that PMs can’t use anything else)
Reporting Display: Resources should report their hours worked every day
Week starts on Monday
Protect user Updates: Restrict updates to Project Web Access
Define Current Tasks: Ours is set to 14 Days
Enabled Team Member Gantt view: This is enabled
Currently we have our My Tasks view grid to display this information (this
was at the requests of the PMs but if you have an arrangement that would be
better I will gladly suggest it to them. Yes, I did make them aware that
with Actual Work Done the tracking progress does not automatically capture an
actual start or finish date but this is what they wanted):
Task Name, Start, Actual Start, Remaining Work, week dates, Finish
We have not changed anything on the settings since moving from dummy
projects to real projects but now we cannot enter time into My Tasks. When
we drill down into a task we also no longer see the time phase grid there
either. I’ve tried opening up all the projects and resaving them and then
republishing them to make sure they are definitely all using the same
tracking method but this has not helped either. We can however, change the
Start, Actual Start, Remaining Work and Finish columns. The days a tasks is
scheduled does highlight like it will allow you to input information but the
days the tasks is not schedule for it doesn’t highlight at all.
I don’t know if this means anything but we have our timesheets turned off
and not displayed in the Quick Launch since it was decided to only enter time
into My Tasks.
In regards to Assignment Owners, if we assign our functional/resource
managers as his/her resource’s owner will both the resource and the manager
see the task in their My Tasks page? Our functional/resource managers want
to see all the tasks his/her resources are assigned. We would like to make
it that if the resource that the PM assigned to a project had and emergency
the manager would be able to reassign the task to a different resource (after
that informed the PM of course) so the project plan doesn’t get pushed out
due to the unavailable resource. If using Assignment Owners do not allow
both the manager and resource see the tasks do you have any suggestions on
how we can make it so managers can see the tasks his/her team is working on
in Project Web.
If my questions aren’t clear I am sorry! I tried to provide as much
information as I could. If you are not sure what I am asking please let me
know and I will try to explain our situation better.
Thank you in advance for all your assistance!
Tuckey