F
Frank
Hi,
We are currently in the implementation phase of Project Server 2007 and have
some issues with the Timesheets that compromise the data integrity in the
system. We are running Project Server 2007 SP1 with no specific Add Ons.
Below you'll find our results after testing the scenario's multiple times
(also in the Microsoft EPM Solution VPC):
Scenario I:
When a resource has Saved and Submitted a Project Server 2007 Timesheet to
his/her Timesheet Manager then the resource can still recall, adjust and
delete the Timesheet even after the Timesheet Manager has approved the
Timesheet.
Scenario II:
Same situation as above but when the corresponding period has been closed as
well then the resource can still recall the Timesheet, can no longer adjust
the information in the Timesheet but can still delete the Timesheet.
To us this is a very unwanted situation, in our opinion a resource should
not be able to recall a Timesheet after this Timesheet has been approved by
the Timesheet Manager. Approving the Timesheet should fixate it's status for
the resource. Only the Timesheet Manager should be able to recall the
approved Timesheet until the corresponding period has been closed, after
closing the period nobody should be able to make adjustments in the
Timesheets for that period any longer.
Hope this explains the situation we are currently dealing with. Don't
hesitate to contact me if more information is needed.
Best regards,
Frank Jutte
We are currently in the implementation phase of Project Server 2007 and have
some issues with the Timesheets that compromise the data integrity in the
system. We are running Project Server 2007 SP1 with no specific Add Ons.
Below you'll find our results after testing the scenario's multiple times
(also in the Microsoft EPM Solution VPC):
Scenario I:
When a resource has Saved and Submitted a Project Server 2007 Timesheet to
his/her Timesheet Manager then the resource can still recall, adjust and
delete the Timesheet even after the Timesheet Manager has approved the
Timesheet.
Scenario II:
Same situation as above but when the corresponding period has been closed as
well then the resource can still recall the Timesheet, can no longer adjust
the information in the Timesheet but can still delete the Timesheet.
To us this is a very unwanted situation, in our opinion a resource should
not be able to recall a Timesheet after this Timesheet has been approved by
the Timesheet Manager. Approving the Timesheet should fixate it's status for
the resource. Only the Timesheet Manager should be able to recall the
approved Timesheet until the corresponding period has been closed, after
closing the period nobody should be able to make adjustments in the
Timesheets for that period any longer.
Hope this explains the situation we are currently dealing with. Don't
hesitate to contact me if more information is needed.
Best regards,
Frank Jutte