M
Mauricio@BVFG
This is a very interesting issue:
1) PM assigns a resource (TM) to a task (let's asume a 4 hours task) and
publishes the project
2) TM reports time in PWA. Let's asume TM presses the 6 by mistake. Why the
Work is being increased from 4 to 6 hours? Note that the "Save All" or
"Update All" buttons have not being pressed.
3) The resource realizes the error and enters 4 hours for the task, PWA does
not fix the Work field. It keeps showing the 6 hours. TM Presses "Update All"
4) PM accepts the update. PWA is now pushing two extra hours to the task!!
This makes no sense at all!!!
Please help!!!
Thanks
Mauricio Iannini, PMP MsP Black Belt
1) PM assigns a resource (TM) to a task (let's asume a 4 hours task) and
publishes the project
2) TM reports time in PWA. Let's asume TM presses the 6 by mistake. Why the
Work is being increased from 4 to 6 hours? Note that the "Save All" or
"Update All" buttons have not being pressed.
3) The resource realizes the error and enters 4 hours for the task, PWA does
not fix the Work field. It keeps showing the 6 hours. TM Presses "Update All"
4) PM accepts the update. PWA is now pushing two extra hours to the task!!
This makes no sense at all!!!
Please help!!!
Thanks
Mauricio Iannini, PMP MsP Black Belt