A
ankitjain.ymca
We have an issue regarding the tasks update options:-
-------------------------------------------------------------------------------
The settings we define ( for example, daily or weekly, group by
owner, and filter settings etc...) are not kept when you accept or
reject the "Tasks Updates" OR you visit the page next time ,
UNLIKE those settings are saved in "Project Center" and "Resource
Center".
ALSO we do not have any views for the "Tasks Updates" page in PWA 2007
which can be
customized for a particular "Group By" OR "Filter settings" etc.
I want to know if anything can be done in this regards because the
project leader has to redo the filter for each task he want to update.
Thanks in Advance.
Best Regards,
Ankit Jain.
-------------------------------------------------------------------------------
The settings we define ( for example, daily or weekly, group by
owner, and filter settings etc...) are not kept when you accept or
reject the "Tasks Updates" OR you visit the page next time ,
UNLIKE those settings are saved in "Project Center" and "Resource
Center".
ALSO we do not have any views for the "Tasks Updates" page in PWA 2007
which can be
customized for a particular "Group By" OR "Filter settings" etc.
I want to know if anything can be done in this regards because the
project leader has to redo the filter for each task he want to update.
Thanks in Advance.
Best Regards,
Ankit Jain.