S
Sonoma-Rich
I am having a issue with the automatic Roll-up calculation of Physical %
Complete. It sometimes does not calculate the Roll-up value properly. I
need to manually change each value for all the subtask to some other number,
then back to the original number to get the correct roll-up value. This can
be very annoying when I have many tasks to update manually. I tried
selecting the "Calculate Now" button in Tools->Options->Calculation dialog
box, but it does not work. Is there a way to automatically redue the
calculation for Roll-up of Physical % Complete. I am running Project
Standard 2003 with SP3.
Complete. It sometimes does not calculate the Roll-up value properly. I
need to manually change each value for all the subtask to some other number,
then back to the original number to get the correct roll-up value. This can
be very annoying when I have many tasks to update manually. I tried
selecting the "Calculate Now" button in Tools->Options->Calculation dialog
box, but it does not work. Is there a way to automatically redue the
calculation for Roll-up of Physical % Complete. I am running Project
Standard 2003 with SP3.