Issue with BCWP

S

Scott Rosa

I have an issue with a large project plan which has been developed. For some
reason some tasks have BCWP values of 0. These tasks are baselined, have both
% work complete and actual % work complete values of 100% as well as Actual
start and finish dates. The status date is set to the current date. Any idea
why this is not calculating?

Thanks,

Scott
 
S

Scott Rosa

Thanks for replying Jack. Yes, we have resources assigned to all the tasks.
In fact the actual cost is 1million higher than BCWP.
 