S
Scott Rosa
I have an issue with a large project plan which has been developed. For some
reason some tasks have BCWP values of 0. These tasks are baselined, have both
% work complete and actual % work complete values of 100% as well as Actual
start and finish dates. The status date is set to the current date. Any idea
why this is not calculating?
Thanks,
Scott
reason some tasks have BCWP values of 0. These tasks are baselined, have both
% work complete and actual % work complete values of 100% as well as Actual
start and finish dates. The status date is set to the current date. Any idea
why this is not calculating?
Thanks,
Scott