R
RobH
Hi,
Trying to import schedule to Cobra and having an issue with the WBS number
field. Cobra engine doesn't like a zero level WBS. If you display the
project summary task, the import will fail. Removed the summary task and
tried again, failed. What I want is for the project to be WBS level zero,
and the major elements 1.0, 2.0, etc. Cobra seems to want the project to be
WBS level 1.0, and the major elements 1.1, 1.2, etc. Anyone run into this
before?
Thanks,
RobH
Trying to import schedule to Cobra and having an issue with the WBS number
field. Cobra engine doesn't like a zero level WBS. If you display the
project summary task, the import will fail. Removed the summary task and
tried again, failed. What I want is for the project to be WBS level zero,
and the major elements 1.0, 2.0, etc. Cobra seems to want the project to be
WBS level 1.0, and the major elements 1.1, 1.2, etc. Anyone run into this
before?
Thanks,
RobH