Issue with linking an assignment in PWA Timesheet

M

Mickneil

Hello,

The following message is displayed in Project Web Access when I attempt to
link a task assignment on my timesheet to an issue/risk.

Error Message:
"You cannot link issues to this task for the following reason:
- The task is a newly created task that has not been approved by the
manager."

This assignment was one that was added to my timesheet using “Assign myself
to an existing taskâ€. The assignment has been accepted and updates have been
applied many times.

I have “republished assignments†taking ownership and the error message
still appears when I try to link a issue/risk/document to this task from the
Timesheet screen.

Has anyone encountered this message before and is there a way to work around
this?

Thanks in advance
Mickneil
 