I'm experiencing an issue with a handful of task plans in which the task is
marked complete (remaining wk = 0, % Wk = 100, Actual finish populated), but
when I sync with protected actuals, the remaining work for certain resources
is changed back to 1 and the task is reopened. The tasks start out as fixed
duration, non effort driven, but are changed to fixed work when the task is
closed. The resources have no actual work and in the MPWA timesheets
(according to the View Resource Assignments page) is set to zero. Any
suggestions on why this is happening or how to prevent it would be greatly
appreciated.
marked complete (remaining wk = 0, % Wk = 100, Actual finish populated), but
when I sync with protected actuals, the remaining work for certain resources
is changed back to 1 and the task is reopened. The tasks start out as fixed
duration, non effort driven, but are changed to fixed work when the task is
closed. The resources have no actual work and in the MPWA timesheets
(according to the View Resource Assignments page) is set to zero. Any
suggestions on why this is happening or how to prevent it would be greatly
appreciated.