G
Guest
Hi
A resource entering his time against a project called "A". But, for that
project the hours he accounted are not showing up for administrator or for
the resource (actuals he posted).
For that project only, the hrs are missing. Couple of days back, that
resource requested the project manager to assign more hrs for that project
as the % work complete shows 100%.
The project manager increased the hrs and published the project schedule.
But, I am completely lost how the hrs for that resource for that particular
project "A" were missing. The project manager approves the hrs of that
resource on a daily basis.
Please revert with some ideas on how this would happen.
Thank you
Shiva Chaitanya.
A resource entering his time against a project called "A". But, for that
project the hours he accounted are not showing up for administrator or for
the resource (actuals he posted).
For that project only, the hrs are missing. Couple of days back, that
resource requested the project manager to assign more hrs for that project
as the % work complete shows 100%.
The project manager increased the hrs and published the project schedule.
But, I am completely lost how the hrs for that resource for that particular
project "A" were missing. The project manager approves the hrs of that
resource on a daily basis.
Please revert with some ideas on how this would happen.
Thank you
Shiva Chaitanya.