G
George F
I published some tasks a couple of days ago to one of our schedules. The
resources that were assigned the tasks were able to see them in their
timesheets and update the tasks (add time to them) but I can't see these
tasks in the schedule in web access when I look in there (when I access the
schedule through the client, I'm able to see them there). Also the updates
that have been applied to the new tasks are not getting added to the totals
in the portfolio analyzer. We're using MSP Professional 2003 and MSP Server
2003.
Any thoughts on this anyone?
resources that were assigned the tasks were able to see them in their
timesheets and update the tasks (add time to them) but I can't see these
tasks in the schedule in web access when I look in there (when I access the
schedule through the client, I'm able to see them there). Also the updates
that have been applied to the new tasks are not getting added to the totals
in the portfolio analyzer. We're using MSP Professional 2003 and MSP Server
2003.
Any thoughts on this anyone?