G
Garon
We have changed the Project Option Settings - Calculation Tab
- Calculation Options to move start & end of completed parts to the Status
Date. All 4 options are checked (ON).
We have then defined the following tasks
Task 1 - Start on project start 08/22/05 - Work & Duration = 4d
Task 2 - Successor to Task 1 (1FS+5Days) - Planned Start = 08/26/05
- Work & Duration = 3d, Planned Finish 09/06/05
Task 3 - Successor to Task 2 (2FS) - Planned Start = 09/07/05
- Work & Duration = 1d, Planned Finish 09/07/05
We assigned and published the tasks and later in PWA the users start to
Status their assignments.
Status Date = Current Date (08/31/05)
The user has completed Task 2 early (worked hard and finished today) althoug
the tasks was scheduled to be finished on 09/06/05 (Next week).
After updating the PM and getting the update approved we review the details
in Project Professional. There is only a single resource assigned to the
Task.
The Gantt Chart View (Task View) shows the Task Finish Date and Actual
Finish Date are both showing 09/06/05, which we believe is incorrect.
The Task Usage for the Task (Assignments View) shows;
Task Finish and Actual Finish are both showing 09/06/05 - incorrect.
Assignment Finish and Assignment Actual Finish are both showing 08/31/05,
which we believe is correct.
The worst issue is that Task 2 Successor (Task 3) remains with a Start Date
of 09/07/05 and does not reset to allow an earlier start.
All Tasks are defined to "Start As Soon As Possible".
If the predecessor Task is finished early and I a task is set to "Start As
Soon As Possible" surely the task should reschedule to start all path
threads earlier.
QUERIES
a) Has anyone found a way to overcome this issue
b) Is this a fault or functional limitation
c) Is there some way around this or a process that can be run to update the
path correctly.
- Calculation Options to move start & end of completed parts to the Status
Date. All 4 options are checked (ON).
We have then defined the following tasks
Task 1 - Start on project start 08/22/05 - Work & Duration = 4d
Task 2 - Successor to Task 1 (1FS+5Days) - Planned Start = 08/26/05
- Work & Duration = 3d, Planned Finish 09/06/05
Task 3 - Successor to Task 2 (2FS) - Planned Start = 09/07/05
- Work & Duration = 1d, Planned Finish 09/07/05
We assigned and published the tasks and later in PWA the users start to
Status their assignments.
Status Date = Current Date (08/31/05)
The user has completed Task 2 early (worked hard and finished today) althoug
the tasks was scheduled to be finished on 09/06/05 (Next week).
After updating the PM and getting the update approved we review the details
in Project Professional. There is only a single resource assigned to the
Task.
The Gantt Chart View (Task View) shows the Task Finish Date and Actual
Finish Date are both showing 09/06/05, which we believe is incorrect.
The Task Usage for the Task (Assignments View) shows;
Task Finish and Actual Finish are both showing 09/06/05 - incorrect.
Assignment Finish and Assignment Actual Finish are both showing 08/31/05,
which we believe is correct.
The worst issue is that Task 2 Successor (Task 3) remains with a Start Date
of 09/07/05 and does not reset to allow an earlier start.
All Tasks are defined to "Start As Soon As Possible".
If the predecessor Task is finished early and I a task is set to "Start As
Soon As Possible" surely the task should reschedule to start all path
threads earlier.
QUERIES
a) Has anyone found a way to overcome this issue
b) Is this a fault or functional limitation
c) Is there some way around this or a process that can be run to update the
path correctly.