It's hard to plan :)

  • Thread starter Mindaugas Bliûdþius
  • Start date
M

Mindaugas Bliûdþius

Hi,

I have project witch already started, but there was no plan developed for
this project. Now I desided to develop plan for this project and continue to
work. In this plan same tasks already finished (like Software Functional
Specification) but i don't know how long it was or who did it (beleave it's
happens :) But i want these task be visible in plan. How can i represent
them? Must they be 0 duaration with no resources? Or maybe i can assign
resources to them and simbolic duaration? But I want that MSProject start
calculating everything just from that moment went i publihed the plan (let's
say from Bug fixing in beta release :)

Thank's.

P.S. The problem can be discribed like this too: I used template, but i can
see that i'm somewhere in the middle of work, how to force MSProject
calculate everything just from that point in template where i want and don't
mind what was planned before and what resources was assignet to them by
template (but i whant them to be as such that everyone could see how much we
missed to plan :). Maybe someone can help me on using templates? (some links
or something...)
 
J

Jan De Messemaeker

Hi,

For all finished tasks, put them to 100% complete.
Then you can set whatever dates, Project wi.ll no longer recalculate
When that is doen, go to Tools, tracking, update Project, to shift teh
remainig work to tomaoorow or later.
HTH
 