In Project Server, is there a maximum number of jobs you can assign per task in a project

Thanks for any help
Jessica
 
J

John

Jessica,
If you mean resource assignments per task, the specification for Project
does not say. It may vary somewhat depending on which version of Project
you are using, but for Project 2000 these are the limits with regard to
tasks and resources:
Tasks per project file: 1 million
Resource per project: 1 million
Resource units per assignment: 10,000 or 1 million percent.

Hope this helps.
John
 
J

Jessica

Thanks for the feedback. The question really should have been worded how many tasks can be assigned per project for Project Server 2003 which John answered for me. Thanks again

-Jessica
 