I have a summary project consisting of many inserted
projects, all using the same resource pool. I rearranged
many of the projects from within the summary project by
changing their caluculation method from the start date of
the project to the finish date.

I opened all of the projects and save all including the
resource pool. Now when I attempt to do just about
anything in the summary project, many (not all) of the
projects that I rearranged jump to some common finish
date. If I open the indidvidual project it corrects
itself. Any additional work within the summary project
will cause it to jump again.

Any ideas? This is driving me nuts!

Thanks,

Tim
 
J

Jan De Messemaeker

Hi Tim,

In Tools, Options, Calculation, cross out
"Inserted projects are calculated like summary tasks"
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top