Keep duration, redistribute remaing work after actual work reporte

R

Richard P

How do I...

Objective is to have the remaining work increase/decrease based on actual
work reported without impacting the task duration.

Example:

5 day task
Resource assigned with work of 40 hours

On day 1 report 0 actual work
Would like the 40 hours of work to be distributed across the remaining 4 days

On day 2 report 16 hours actual work
Would like the 24 hours of remaining work to be distributed across the
remaining 3 days
 
R

Rod Gill

Hi,

Set the Task Type to Fixed duration. As you update Actual work in a usage
view, the remaining work gets recalculated and the duration stays the same.

Window, Split or look at the advanced tab in the Task information dialog to
edit task type.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top