R
Richard P
How do I...
Objective is to have the remaining work increase/decrease based on actual
work reported without impacting the task duration.
Example:
5 day task
Resource assigned with work of 40 hours
On day 1 report 0 actual work
Would like the 40 hours of work to be distributed across the remaining 4 days
On day 2 report 16 hours actual work
Would like the 24 hours of remaining work to be distributed across the
remaining 3 days
Objective is to have the remaining work increase/decrease based on actual
work reported without impacting the task duration.
Example:
5 day task
Resource assigned with work of 40 hours
On day 1 report 0 actual work
Would like the 40 hours of work to be distributed across the remaining 4 days
On day 2 report 16 hours actual work
Would like the 24 hours of remaining work to be distributed across the
remaining 3 days