M
Microsoft Communities
Hi all,
I have a task A with 4 hours (work), and resource work 8 hours/day so task
A's duration is 0.5 days. When I publish task A to project server and
project member input actual value on PWA, task A is 3 hours (0.375 days
duration) and finished (set remaining work of task A = 0).
I accept this task, and the duration of this task on my schedule change to 1
day, so all task linked to task A change. How can force ms project calculate
right duration on actual value?
Thanks
I have a task A with 4 hours (work), and resource work 8 hours/day so task
A's duration is 0.5 days. When I publish task A to project server and
project member input actual value on PWA, task A is 3 hours (0.375 days
duration) and finished (set remaining work of task A = 0).
I accept this task, and the duration of this task on my schedule change to 1
day, so all task linked to task A change. How can force ms project calculate
right duration on actual value?
Thanks