Phillip Armitage
I'm having problems with split tasks. I can define the task and split it,
but Project won't seem to let me specify the exact start and end dates of
the task components. For instance, let's say I have a task I want to start
Monday, work on until Friday then a week later I want to start work on it
again on the Monday and end on the Friday. So, that's two 5 day sections.
Is there a form/view where, having split a task, I can now go to it and key
in/specify the actual start and end dates of each section? i.e. I don't want
to be playing with a mouse, dragging sections back and forth until I get it
to fit right.
but Project won't seem to let me specify the exact start and end dates of
the task components. For instance, let's say I have a task I want to start
Monday, work on until Friday then a week later I want to start work on it
again on the Monday and end on the Friday. So, that's two 5 day sections.
Is there a form/view where, having split a task, I can now go to it and key
in/specify the actual start and end dates of each section? i.e. I don't want
to be playing with a mouse, dragging sections back and forth until I get it
to fit right.