KPI in Workspace

R

reza

Hi Guys,

PS 2007, MOSS 2007 & SQL Server 2005 Ent
Just wondering, can we set KPI based on project schedule??
maybe someone have doc, article or link about this one?

thanks

reza
 
G

Gary L. Chefetz

Reza:

Most people use Cost, Duration, or Work variance to apply quantitative
measures to project performance or they use Earned Value methods. Variance
measurement formulas can be anything you can write a formula for. How to use
earned value methods is discussed in almost every book every published about
project management.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top