J
Johnny Bravo
Hi all,
I'm still a bit new to laying out projects in MS project, but I think I have
a pretty good understanding of the basics. I seem to be having a little
difficulty trying to finish laying out estimate project costs for labor.
We're a construction firm with residential home improvement jobs for our
projects. We're entering one job (customer) per project and allocating labor
resources as generic labor for estimating purposes. Even though we have the
same crews work on all the projects, I figured it made the most sense to set
each clinet up as a separate job
My question relates to the display of costs in the Reports section for
allocated resources.
Our use of Project is to keep track of estimated task time (Usually by
10-hour day) compared to actual time spent to complete the job. We're looking
to keep track of time and labor (by job phase) remaining as well.
The simple question:
I've entered the estimated labor resource (1-man labor of $35/hour) and
allocated it to every task in the project where needed. That put a standard
$35/hour rate into the cost for every estimated labor hour specificed.
When I went to check the costs., I looked at one phase that called for 2
days of labor by one man. ... 2 (two) x 10 hour days. As I understand the
software, the cost report should be showing up with $700 labor cost
(estimated) per (10 hour)day, actually shows up as $735 per day.
This happened in every task, for every respurse we've assigned, including
truck time.
Why the extra hour?
Estimated resource shows "2d?" as the estimated duration of the task.
~~~~~~~~~~~~~~~~~~~~~~
www.drakeleypools.com~~~~~~~~~~~~~~~~~~~~~~
I'm still a bit new to laying out projects in MS project, but I think I have
a pretty good understanding of the basics. I seem to be having a little
difficulty trying to finish laying out estimate project costs for labor.
We're a construction firm with residential home improvement jobs for our
projects. We're entering one job (customer) per project and allocating labor
resources as generic labor for estimating purposes. Even though we have the
same crews work on all the projects, I figured it made the most sense to set
each clinet up as a separate job
My question relates to the display of costs in the Reports section for
allocated resources.
Our use of Project is to keep track of estimated task time (Usually by
10-hour day) compared to actual time spent to complete the job. We're looking
to keep track of time and labor (by job phase) remaining as well.
The simple question:
I've entered the estimated labor resource (1-man labor of $35/hour) and
allocated it to every task in the project where needed. That put a standard
$35/hour rate into the cost for every estimated labor hour specificed.
When I went to check the costs., I looked at one phase that called for 2
days of labor by one man. ... 2 (two) x 10 hour days. As I understand the
software, the cost report should be showing up with $700 labor cost
(estimated) per (10 hour)day, actually shows up as $735 per day.
This happened in every task, for every respurse we've assigned, including
truck time.
Why the extra hour?
Estimated resource shows "2d?" as the estimated duration of the task.
~~~~~~~~~~~~~~~~~~~~~~
www.drakeleypools.com~~~~~~~~~~~~~~~~~~~~~~