J
Jack Dahlgren MVP
This problem sounds like you are using summary task links so I'm assuming
that you have set the summary task for sect a to be the predecessor of
summary task b.
Then the predecessor of task be would ONLY be task A and enter the 50%
against that.
If you do this then you won't have to set a start task for section b.
I don't find it good practice to link summary tasks, but it sounds like this
is the way your project is set up.
-Jack Dahlgren
that you have set the summary task for sect a to be the predecessor of
summary task b.
Then the predecessor of task be would ONLY be task A and enter the 50%
against that.
If you do this then you won't have to set a start task for section b.
I don't find it good practice to link summary tasks, but it sounds like this
is the way your project is set up.
-Jack Dahlgren