T
TMBoyle
I am using MSP 2003 (Std) on a large engineering and construction project
where some tasks are scheduled on a 7-day work week and some are scheduled on
a 5-day work week. I am becoming more confused regarding MSP's schedule
computations when lagging relationships and such non-standard task calendars
are involved. I have read in this forum and elsewhere that MSP uses the
Project Calendar to account for lag time, but the results in my working
schedule are not consistent with this.
To check, I prepared a little three-task A-B-C network. For simplicity,
all three tasks are fixed duration tasks of 20d with no resources. A is the
predessessor of both B (SS+10d) and C (FF+10d). I then systematically
switched the task calendars for A, B, and C between "None" (i.e. the Standard
Project Calendar, 5-day workweek), and a newly-created 7-day workweek. In
all cases, the start dates for the successor activities accounted for the
specified lag based on the SUCCESSOR TASK CALENDAR, not the Project Calendar.
Can someone else please repeat this 10-minute exercise and confirm the same
result?
In the current project, I have a number of construction activities with a
7-day task calendar, while the overall project calendar is a 5-day calendar.
I ignore weekends in specifying the lag times between these activities (i.e.
7d lag is Monday-to-Monday, not Monday-to-Wednesday), and they have all been
scheduled correctly. This would not have occurred if the Project Calendar
was the basis for all lag calculations.
So, is the schedule impact of lag actually computed using the Successor Task
Calendar as observed, not the Project Calendar as commonly stated?
Thanks for any and all contributing opinions.
tmb
where some tasks are scheduled on a 7-day work week and some are scheduled on
a 5-day work week. I am becoming more confused regarding MSP's schedule
computations when lagging relationships and such non-standard task calendars
are involved. I have read in this forum and elsewhere that MSP uses the
Project Calendar to account for lag time, but the results in my working
schedule are not consistent with this.
To check, I prepared a little three-task A-B-C network. For simplicity,
all three tasks are fixed duration tasks of 20d with no resources. A is the
predessessor of both B (SS+10d) and C (FF+10d). I then systematically
switched the task calendars for A, B, and C between "None" (i.e. the Standard
Project Calendar, 5-day workweek), and a newly-created 7-day workweek. In
all cases, the start dates for the successor activities accounted for the
specified lag based on the SUCCESSOR TASK CALENDAR, not the Project Calendar.
Can someone else please repeat this 10-minute exercise and confirm the same
result?
In the current project, I have a number of construction activities with a
7-day task calendar, while the overall project calendar is a 5-day calendar.
I ignore weekends in specifying the lag times between these activities (i.e.
7d lag is Monday-to-Monday, not Monday-to-Wednesday), and they have all been
scheduled correctly. This would not have occurred if the Project Calendar
was the basis for all lag calculations.
So, is the schedule impact of lag actually computed using the Successor Task
Calendar as observed, not the Project Calendar as commonly stated?
Thanks for any and all contributing opinions.
tmb