S
Shawn Everingham
I have hopefully not a unique case here, so thought I'd see if there was
solution or idea that would work for us in this case.
Task 1 is linked to Task 2....
Task 2 is an 8hr piece of work accomplished by a business user (who doesn't
use PWA or Project) Task 2 is linked to Task 3.
Task 3 really needs to start one day after Task 1 finishes.
We need to account for a 1 day padding between Task 1 and Task 3. How do we
do that? Task 2 will never get updated by any resource, so we basically need
Task 2 to be a stop watch. We may not even need Task 2.
I was trying to set a formula for Task 3 to be = Actual Finish Date of Task
1 + 1 day...I don't seem to be able to do that?
How can I dynamically set a task start date to be the finish date of a
previous task + some amount of time?
Hope I"m making sense here...Let me know if not. THanks in advance!
Shawn
solution or idea that would work for us in this case.
Task 1 is linked to Task 2....
Task 2 is an 8hr piece of work accomplished by a business user (who doesn't
use PWA or Project) Task 2 is linked to Task 3.
Task 3 really needs to start one day after Task 1 finishes.
We need to account for a 1 day padding between Task 1 and Task 3. How do we
do that? Task 2 will never get updated by any resource, so we basically need
Task 2 to be a stop watch. We may not even need Task 2.
I was trying to set a formula for Task 3 to be = Actual Finish Date of Task
1 + 1 day...I don't seem to be able to do that?
How can I dynamically set a task start date to be the finish date of a
previous task + some amount of time?
Hope I"m making sense here...Let me know if not. THanks in advance!
Shawn