Q
quixote
Fairly new to Project so bear with me.
I have a sub task that was scheduled and finished on 1/7/09. The next sub
task is schedule to start 9/1/09...almost 8 months later. When someone
changed this date the summary progress bar on the Gantt makes it look like
the main task is almost complete even though it say 19%...can someone help me
how to handle this large gap in time in which no work will be done between
the 2 tasks?
I have a sub task that was scheduled and finished on 1/7/09. The next sub
task is schedule to start 9/1/09...almost 8 months later. When someone
changed this date the summary progress bar on the Gantt makes it look like
the main task is almost complete even though it say 19%...can someone help me
how to handle this large gap in time in which no work will be done between
the 2 tasks?