Lag

D

DanM

Hello,

Can any one tell me witch calendar the lag is using?

What I mean is:

I have 2 activities. A and B, A is driving B with a lag. A has on
calendar and B has another calendar. Witch calendar is the lag using?

Regards

Da
 
J

Jim Aksel

Microsoft Project uses the following types of calendars to determine resource
availability and the way tasks are scheduled:

Base calendar
A base calendar is used as a *template* that the project calendar (project
calendar: The base calendar used by a project.), resource calendars or task
calendars are based on. Three base calendars are provided with Project:

•Standard (8:00 A.M. to 5:00 P.M. weekdays, with an hour off for lunch)
•24-Hours
•Night Shift

So the base calendar is the template. If you make a new calendar, base it
off one of these. By default, the Standard calendar is assigned as the
Project Calendar for projects and project tasks.

What we do is make a copy of the Standard Calendar and call it "Company
Calendar". We input company holidays, shut down time, etc. We then assign
"Company Calendar" as the "Project Calendar" in Project/Project Options...

So to directly answer the question, the calendar assigned to predecessor is
the calendar of the successor (Task B). If Task B does not have a calendar
assigned to it, then project uses the same calendar that appears in
Project/Project Options.

If that calendar name happens to be one of the three base calendar names,
then so be it.

The point is subtle and probably I am being Nit Picky ... at any rate, I
gave you the two places to look for the calendar that will govern how lag is
handled in a predecessor/successor relationship.

--
Jim Aksel, MVP

Check my blog for more info:
http://www.msprojectblog.com

This newsgroup is moving, try here too:
http://social.answers.microsoft.com/Forums/en-US/addbuz/threads
 
J

Jim Aksel

It will use what ever calendar is assigned to task B. If B has no assigned
calendar the the project calendar is used.

To check calendars:

Project Calendar: On the menu: Project/Project Information. The default is
"Standard"
For a task, double click the task to view the Task Information dialog box.
Pull the Advanced tab and look under Calendar. If the task calendar is
"none" then it is using the Project Calendar.
--
Jim Aksel, MVP

Check my blog for more info:
http://www.msprojectblog.com

This newsgroup is moving, try here too:
http://social.answers.microsoft.com/Forums/en-US/addbuz/threads
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top