G
glen.e.mettler
Using 2003
I am evaluating a project that has lots of large lags - FS & SS
I need to reduce the overall project duration by 10%.
I have reduced all of the critical path and near critical path tasks by
10%.
However, the lags are posing a problem with final reviews and delivery
dates because the lag is hard coded. This is especially true of the SS
lags.
Is there a way I can reduce these long lags by 10% (say anything
greater than 90 days)?
There are over 1000 of these. I don't like the idea of going thru each
one manually. Or is there a macro someone has already created that I
can run that would do it?
Any thoughts?
Glen
I am evaluating a project that has lots of large lags - FS & SS
I need to reduce the overall project duration by 10%.
I have reduced all of the critical path and near critical path tasks by
10%.
However, the lags are posing a problem with final reviews and delivery
dates because the lag is hard coded. This is especially true of the SS
lags.
Is there a way I can reduce these long lags by 10% (say anything
greater than 90 days)?
There are over 1000 of these. I don't like the idea of going thru each
one manually. Or is there a macro someone has already created that I
can run that would do it?
Any thoughts?
Glen