Large Lag Times

R

reppuccibh

I've recently taken over a very large schedule that has about 15
projects linked together, its been running for a few years and has many

more to go, this is my question 'Is there any way to show lag times
only' as the previous owners liked to link tasks using very large lag
times.
 
R

Reid McTaggart

I'm not sure if this is what you have in mind, but you can display a task's
predecessor(s), including lead/lag, on the Gantt chart by modifying the Bar
Styles and selecting Predecessor for one of the Text fields to display.
 
R

reppuccibh

Not exactly, what I was looking for was a way to filter and show - say
tasks that have lead/lag greater than 50 days instead of all of them -
which are numerous.
 