lead and lag

T

toyosi

hi, i have these two tasks. i want the succeding one to start two days into the preceding one, should i give it a dependency type of finish - start with 2 days lead(i.e -2days)?or is it start- start of -2days?confuse
cheers
 
J

Jan De Messemaeker

Hi,

It is Finish to Start

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
toyosi said:
hi, i have these two tasks. i want the succeding one to start two days
into the preceding one, should i give it a dependency type of finish - start
with 2 days lead(i.e -2days)?or is it start- start of -2days?confused
 
L

lead and lag

Please i still dont get you quite clearly. may be i should frame it this way: a preceding tasks has a duration of 20d and its suceesor has a 6d duration, also i want the successor to start say the 2nd day into the preceeding tasks, should
i give the successor a dependency of -2day finist to start?
 
J

Jan De Messemaeker

Hi,

Indeed that was not quite clear to me.

If you want the successor to start on day 3, then it is SS+2 days
If you want the successor to start on day 19, it is FS-2d

If we still misunderstand each other: it is faster to try it!

Greetings,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
lead and lag said:
Please i still dont get you quite clearly. may be i should frame it this
way: a preceding tasks has a duration of 20d and its suceesor has a 6d
duration, also i want the successor to start say the 2nd day into the
preceeding tasks, should
 
S

Steve House

You could do a SS link with a *lag* (not lead) of 2 days or you could do it
with a FS link with a *lead* of the predecessor's duration minus 2 days (ex:
if the predecessor is 8 days long, the FS lead time is -6 days, NOT -2
days). Either way is correct, to choose which you use, ask yourself in the
process itself, which end of the predecessor is the determining factor for
the timing of the sucessor, its start or its finish.

Lead time means that successor starts earlier than the link otherwise would
place it, lag time means it starts later than the link would place it.

--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

toyosi said:
hi, i have these two tasks. i want the succeding one to start two days
into the preceding one, should i give it a dependency type of finish - start
with 2 days lead(i.e -2days)?or is it start- start of -2days?confused
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top