Leading dots on task bars

D

David L.

I have created custom work contours for my tasks and although I do not have
any splits in the work, I keep seeing leading dots in front of each bar on
the Gantt. I have tried to zero out the value in the cells on task usage but
the problem persists.
I have also tried to change the task type from fixed duration to fixed work
or fixed units and it doesn't help. I am using MSP 2000.

Any idea?

David.
 
J

Jan De Messemaeker

Hi,

Double-click on the assignment line in Tak usage to show ssignment
information, then set the assignment start date equal to the task start
date.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top