E
exsyfg
Hi all,
We've introduced the lean-concept within our company, and now we are in
the stage were we need to adapt our way of planning work for our group
:
You need to take into account that :
- The ideal time to execute task A = 1 md (the average of a senior
system engineer)
- The real time to execute task A could be 1 to 3 md following the
experience of the guy executing the task
How can we put something like this into ms project ?
Working with 'work' and 'duration' doesn't solve my problem, as i.e. :
- if i change the duration to 3 md
- MS project does not increase the work for the guy, to occupy him 3
days, but spreads the 1 md over 3 md, giving the guy the opportunity to
do something else
- overload = guaranteed this way.
Is there somebody over here that has idea's on how to tackle this
within MS-Project ?
The aim is to measure the variance between people, and the progress
made during time.
All help really appreciated !
Kind regards,
Franky.
We've introduced the lean-concept within our company, and now we are in
the stage were we need to adapt our way of planning work for our group
:
You need to take into account that :
- The ideal time to execute task A = 1 md (the average of a senior
system engineer)
- The real time to execute task A could be 1 to 3 md following the
experience of the guy executing the task
How can we put something like this into ms project ?
Working with 'work' and 'duration' doesn't solve my problem, as i.e. :
- if i change the duration to 3 md
- MS project does not increase the work for the guy, to occupy him 3
days, but spreads the 1 md over 3 md, giving the guy the opportunity to
do something else
- overload = guaranteed this way.
Is there somebody over here that has idea's on how to tackle this
within MS-Project ?
The aim is to measure the variance between people, and the progress
made during time.
All help really appreciated !
Kind regards,
Franky.