Hi All
Is it possible to get a report on leave recorded in
Project (am using 2002 std)?
I record all leave for a resource pool in Tools, CWT; and
have set up a copy of the Std to use as the base calendar.
The scheduling is working well, but I can't produce a
report or view for team leaders that shows eg that Res 1
is on leave from 6th Sept to 10th Sept. Something they can
stick on their wall, and look at.
The Calendar View shows tasks, and Resource Calendar non-
working days, but nothing at the resource level.
Thanks
Is it possible to get a report on leave recorded in
Project (am using 2002 std)?
I record all leave for a resource pool in Tools, CWT; and
have set up a copy of the Std to use as the base calendar.
The scheduling is working well, but I can't produce a
report or view for team leaders that shows eg that Res 1
is on leave from 6th Sept to 10th Sept. Something they can
stick on their wall, and look at.
The Calendar View shows tasks, and Resource Calendar non-
working days, but nothing at the resource level.
Thanks