R
Robin Rice
We have EPK sitting on top of MS Project Server, so the answer may be a
little different from the standard project server answer. We cannot get
actuals entered against UNASSIGNED tasks to progress back to the project
schedule correctly.
Is it possible to leave a project task UNASSIGNED to any particular
resource, so that ANYONE who is officially assigned to the team itself can
enter time against it?
For example, we have a task called "Unplanned app dev work". We want anyone
who is part of the project team to be able to get in and enter time against
the task. Then we need to progress the task back to MS Project.
Any ideas would be welcome.
Thanks
Robin
little different from the standard project server answer. We cannot get
actuals entered against UNASSIGNED tasks to progress back to the project
schedule correctly.
Is it possible to leave a project task UNASSIGNED to any particular
resource, so that ANYONE who is officially assigned to the team itself can
enter time against it?
For example, we have a task called "Unplanned app dev work". We want anyone
who is part of the project team to be able to get in and enter time against
the task. Then we need to progress the task back to MS Project.
Any ideas would be welcome.
Thanks
Robin