Length/duration of my summary bars wrong in Proj 2007

M

mmckeen

Hi, hoping someone can help. I've noticed that some of the summary tasks are
the wrong length and for the wrong durations to the tasks that they
summarize. For example, I have 3 tasks with the earliest start date of 10/1
and the latest finish is 10/16. The summary task is 10/21 to 11/10, totally
outside of the range. This is appearing in multiple instances, and then
there are some summary tasks that are behaving as expected. Any ideas?
Thanks in advance.
 
M

mmckeen

HI, I had removed the 'fiscal' setting. Recalculating the project seemed to
work, thanks!
 