Thank you both (Mike, Julie). I can see what is happening now. I do not
want to automatically resource level as that would mess up my dates, but I
can see that I have multiple tasks assigned in the same timeframe (8am, 9am)
that total more than 1 hour for a resource. I think I will just have to live
with it as to change it might be a bugar!
I may have screwed up by setting the project default to Fixed Duration, then
entering the resources. I think I want Fixed Units/Effort Driven and I have
set that as the default and changed all the tasks in mass, but not sure how
the tasks with resources already assigned will act. Much more playing to do!
One thing I have concluded...MSP was developed for the "perfectly" built
plan. If everything is not quite perfect, then the tool may do all kinds of
things you don't expect, even if you think you know what effects should
happen.
Isn't there some heuristic I read in one of the Project books that said once
the resources are initially assigned, they will not be affected by duration
changes or something? I know there is some illogical issue with resources
not being affected after initially entered...can you remember?
I think I am fairly well up on MSP and I am certainly learning more as I go,
but sure seems like there is so much to have to set in place that one can
never know it all. I am impressed with the knowledge ya'll display. Heck, I
am a little ol' White Belt at this point and need to get Orange then more,
but not sure I can get there with all the "features" of MSP I must know!
--
Regards,
DJ Huff, PhD, PMP, CISA, ITIL
JulieS said:
Hello DJ,
Please see FAQ 34 at
http://project.mvps.org/faqs.htm
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project