B
Bill
I am testing out Microsoft EPM with Project Pro.
I created a Project and 2 resources. I assigned about 90
tasks to the resources with about 2 - 10 hours per task.
It put all of the tasks to start today. Now one resource
has 360 hours for today with 90 tasks.
If I run the Resource Availability - Work, it shows that
resource has 360 hours for today.
When I click Level Resources, nothing happens. I expected
that Project Pro would spread the tasks out so the poor
soul would only need to work 8 hours per day instead of
360.
Any ideas?
I created a Project and 2 resources. I assigned about 90
tasks to the resources with about 2 - 10 hours per task.
It put all of the tasks to start today. Now one resource
has 360 hours for today with 90 tasks.
If I run the Resource Availability - Work, it shows that
resource has 360 hours for today.
When I click Level Resources, nothing happens. I expected
that Project Pro would spread the tasks out so the poor
soul would only need to work 8 hours per day instead of
360.
Any ideas?