- Joined
- Mar 21, 2017
- Messages
- 1
- Reaction score
- 0
Hi All,
I keep having the same problem with MS Project and I was wondering if you could help?
I'm not able to resolve the resource allocation error/ notification while levelling and thus not able to reseolve the over-allocation of the resource. Somehow MS. Project is planning more than my daily 8 hrs on certain days. Does anyone know what I'm doing wrong? I checked a previous related post but could not solve the problem... Hope you can help
My project:
For levelling I have tried:
Is there something I should or should not do?
Appreciate your help! Thanks in advance!
Cheers,
Kim
I keep having the same problem with MS Project and I was wondering if you could help?
I'm not able to resolve the resource allocation error/ notification while levelling and thus not able to reseolve the over-allocation of the resource. Somehow MS. Project is planning more than my daily 8 hrs on certain days. Does anyone know what I'm doing wrong? I checked a previous related post but could not solve the problem... Hope you can help
My project:
- I'm the only resource (so far) with Max Units of 75% (want to keep 25% as a buffer)
- I have set the working hours at 40hrs per week, 8hrs per day (under options)
- I have used the standard calendar and filled in my working time
- There are tasks with a constraint type as I want some only to occur on a specific date (e.g. re-current meetings). These are not linked to the critical path
- I have set no priorities
- I have allocated 25% Units per task as I want to gradually complete the task.
- "Type" used is fixed work
- All tasks are auto scheduled
For levelling I have tried:
- Level calculations automatic and manual
- Levelling options day by day and week by week
- All the levelling orders except for "level manually scheduled tasks"
Is there something I should or should not do?
Appreciate your help! Thanks in advance!
Cheers,
Kim