S
Scott Diamond
I wonder if anyone can provide assistance on constraining leveling. I want
MS-Project to level my tasks but I'd like for sub-projects to remain grouped
and not be split up. An example may make this clearer.
I'm starting with two tasks pertaining to testing at labs out of state:
Testing in LA---------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska------------
AK Task1 - Joe
AK Task2 - Joe
What I would like is for MS-Project to keep the projects grouped. For
example one could schedule testing in LA before testing in Alaska (but I
want Project to best determine the order). I'd like leveling to produce a
result like:
Testing in LA---------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska-----------
AK Task1 - Joe
AK Task2 - Joe
When I tell Project to level it doesn't work. I end up with scenarios like
that shown below. This is clearly not feasible because Joe cannot instantly
hop from LA to Alaska and I have to reserve lab time in a block.
Testing in LA-----------------------------------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska------------
AK Task1 - Joe
AK Task2 - Joe
I've tried the obvious setting in the level resource dialog box but it will
not do what I want. I could of course go in and set the priority of one set
of tasks higher than another or I could make explicit links but that is
pretty much manual leveling which I do not want to use.
Thanks for any advice. If it matters I'm using MS-Project 2003 SP2
-Scott
MS-Project to level my tasks but I'd like for sub-projects to remain grouped
and not be split up. An example may make this clearer.
I'm starting with two tasks pertaining to testing at labs out of state:
Testing in LA---------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska------------
AK Task1 - Joe
AK Task2 - Joe
What I would like is for MS-Project to keep the projects grouped. For
example one could schedule testing in LA before testing in Alaska (but I
want Project to best determine the order). I'd like leveling to produce a
result like:
Testing in LA---------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska-----------
AK Task1 - Joe
AK Task2 - Joe
When I tell Project to level it doesn't work. I end up with scenarios like
that shown below. This is clearly not feasible because Joe cannot instantly
hop from LA to Alaska and I have to reserve lab time in a block.
Testing in LA-----------------------------------------
LA Task1 - Joe
LA Task2 - Joe
Testing in Alaska------------
AK Task1 - Joe
AK Task2 - Joe
I've tried the obvious setting in the level resource dialog box but it will
not do what I want. I could of course go in and set the priority of one set
of tasks higher than another or I could make explicit links but that is
pretty much manual leveling which I do not want to use.
Thanks for any advice. If it matters I'm using MS-Project 2003 SP2
-Scott