Hello,
I assigned a resource with 100% availability to 2 tasks.
Task A: duration = 2 days with priority 600
Task B: duration = 2 days with prioriy 500
For each task the resource assigned to 50% so I don't have an overallocation
problem.
The resource updated actual time for the first task, the update was 8 hourse
instead of 4 hours.
This update was only for the first day. At the other days he hasn't updated
yet.
At the Gantt I can see that the Max unit equal to 100%, so I understand this
is the pick.
At the Resource usage I see 50% for each day except for the specific day.
Now, I'm trying to level. The result is Task B start after task A finish.
I thought the project will schedule them together from the second day.
Where is the problem ?
Thanks
Perl
I assigned a resource with 100% availability to 2 tasks.
Task A: duration = 2 days with priority 600
Task B: duration = 2 days with prioriy 500
For each task the resource assigned to 50% so I don't have an overallocation
problem.
The resource updated actual time for the first task, the update was 8 hourse
instead of 4 hours.
This update was only for the first day. At the other days he hasn't updated
yet.
At the Gantt I can see that the Max unit equal to 100%, so I understand this
is the pick.
At the Resource usage I see 50% for each day except for the specific day.
Now, I'm trying to level. The result is Task B start after task A finish.
I thought the project will schedule them together from the second day.
Where is the problem ?
Thanks
Perl